UPDATE: Novatek CFO says Yamal LNG 1st stage ready by 94% - News Archive - PRIME Business News Agency - All News Politics Economy Business Wire Financial Wire Oil Gas Chemical Industry Power Industry Metals Mining Pulp Paper Agro Commodities Transport Automobile Construction Real Estate Telecommunications Engineering Hi-Tech Consumer Goods Retail Calendar Our Features Interviews Opinions Press Releases

UPDATE: Novatek CFO says Yamal LNG 1st stage ready by 94%

(Adds paragraph 2)

MOSCOW, Jul 27 (PRIME) -- The first stage of Russia’s Yamal LNG liquefied natural gas plant is 94% ready and the entire project is 85% complete, independent gas producer Novatek CFO Mark Gyetvay said in a presentation seen by PRIME on Thursday.

The executive also said that the company still plans to launch the plant’s first stage until the end of 2017.

The Yamal LNG project envisages construction of a 16.5-million-tonne LNG plant on the basis of the Yuzhno-Tambeiskoye field on the Yamal Peninsula. Novatek holds 50.1% in the project, France’s Total has 20%, China’s CNPC owns 20% and China’s Silk Road Fund holds 9.9%.

End

27.07.2017 17:06
 
 
Share |
To report an error select text and press Ctrl+Enter
 
 
Central Bank Official Rate
1W 1M 1Y
USD
EUR 98.4730 -0.0872 07 may
USD 91.3124 -0.3794 07 may
Stock Market Indices
1D 1W 1M 1Y
MICEX
micex 3436.05 0.00 08:47 07 may
Stock Quotes in RUR
1D 1W 1M 1Y
GAZP
gazp 153.45 -1.13 18:49 06 may
lkoh 7971.00 -1.29 18:49 06 may
rosn 580.90 -0.24 18:49 06 may
sber 306.97 -0.18 18:49 06 may
MICEX Ruble Trading
1D 1W 1M 1Y
USDTD
EURTD 98.1025 -0.4825 14:59 06 may
USDTD 91.1950 -0.2075 17:44 06 may